Projects Related To Forest Clearance
We have working experience of Ten states for Forest Clearance as per provision of FCA, 1980, Wild Life Act, 1972 & Indian Forest Act, 1927. We have in-depth understanding on preparing documents of NOC from National & State Wildlife Board all states of Country. The few projects are listed below:
Sl No. | Project Name | District | State | Project Area (ha.) | Status |
1 | 2×660 MW Coal based Thermal Power Project | Surguja | Chhattisgarh | 300.08 | Project Cleared |
2 | Hydro-structure for 2×660 MW Coal based Thermal Power Project | Surguja, Koriya | Chhattisgarh | 58.9 | Form-3 Stage |
3 | Transmission Line for 2×660 MW Coal based Thermal Power Project | Surguja, Korba, Bilaspur, | Chhattisgarh | 302.7 | Form-4 Stage |
4 | Tara Captive Coal Block for ICPL 2×660 MW Coal based Thermal Power Project | Surguja | Chhattisgarh | 2200 | Project Cleared |
5 | Dumri Coal Mining Project | Hazaribagh | Jharkhand | 158.64 | Project Cleared |
6 | Gargai drinking Water Lifting Scheme in Tansa Wildlife Sanctuary | Thane | Maharashtra | 742.8 | Project Cleared by SBWL |
7 | 2×800 MW Basundhara Thermal Power Project | Sundargarh | Odisha | 58.7 | Form-1 Prepared |
8 | 2×600 MW Bara-darhaa Coal based Thermal Power Project | Jhanjgir-Champa | Chhattisgarh | 12.4 | Project Cleared |
9 | Moher & Moher Amlohri Ext. Coal Block | Singrauli | MP | 1064.02 | Project Cleared |
10 | O.B. Dump and Infrastructure for Moher & Moher Amlohri Ext. Coal Block | Singrauli | MP | 133.28 | Project Cleared |
11 | Chhatrasal Coal Block | Singrauli | MP | 925.10 | Project Cleared |
12 | Siyom Hydro Electric Project | Siyom | Ar. Pradesh | 800.00 | Form-3 Stage |
13 | Tato Hydro Electric Project | Tato | Ar. Pradesh | 867.20 | Project Cleared |
14 | Keredari ‘B’ and ‘C’ captive Coal Block for Tilaiya UMPP | Hazaribagh | Jharkhand | 850 | Form-1 Prepared |